1,750 sold out of 5,100 as of today

Sign up for Updates

* indicates required



I want to receive updates for

Like Fresno Aquarium on Facebook

Dec 2

Work continues on site plan details

Reviewing Fresno Aquarium site plan

December 2, 2013 – Since contracting with Fresno’s Yamabe & Horn Engineering, Inc. for civil engineering in August, Aquarius Aquarium Institute has been working with David Horn, PE to create a new site plan for the first structure of the Fresno Aquarium…

Aug 13

Yamabe & Horn

Yamabe & Horn offices

August 13, 2013 – On Monday night, the Aquarius Aquarium Institute board of directors approved the selection of Yamabe & Horn of Fresno as the Civil Engineers for our Fresno Aquarium life support basement project.

In 2008…

Jun 4

A Gift for Grads and Dads

June 4, 2013 – The Fresno Aquarium would like to suggest a gift idea for both grads and dads – a concrete block! We know it’s not as sexy as a new sports car or a night out on the town, but…

May 4

Whales and Dolphins?


May 4, 2013 – Every so often we receive inquiries asking whether the Fresno Aquarium has plans to exhibit large ocean mammals such as whales and dolphins. It is important for people to know that we have never had plans to exhibit marine mammals such as seals, sea lions, dolphins or whales. The Fresno Aquarium project is not…

Dec 28

From the Ground Up

December 28, 2012 – Have you ever heard of a CMU? A Concrete Masonry Unit is a block that can be lifted by an individual and easily placed to become a part of a much larger wall of a building…

Nov 27

ACE Mentor Program Engages Students

Edison High School students collaborate to design Fresno Aquarium

November 27, 2012 – Today, Aquarius Aquarium Institute founders Tom and Aletha Lang visited Edison High School students in west Fresno to answer questions regarding the students’ design for the Fresno Aquarium.